During 2021 Aarsleff Oy executed 1432 m in diameters DN1300-DN1500, with 10 water cure installations.

During 2022 Aarsleff Oy executed 1662 m in diameters DN1300-DN1800, with 13 water cure installations.

On top of those there was smaller diameter pipes that were executed with steam cure liners.

Many instalations were next to city center underneath busy streets and with bus traffic and school next to site.

All installations were done in normal wastewater pipes and thus regular polyester resin was best solution.